Published schedules
How the forecasts changed
The forecasts below concern construction, design approval, or a return to the committee. Each is paired with the later record. The fiscal year 2026 reports repeatedly moved the expected committee return, then omitted a return date in the year-end report. 26
Forecast made
Expected milestone
Later record
May 2019
Expected milestoneConstruction around August 2020, provided the City approved additional construction funding.8
February 2020
Expected milestoneCommittee recommendation and Council approval in May 2020.10
September 2022
Expected milestoneA return to the committee around September 2023.4
Later recordThe project returned on November 15, 2023.14
July 2024
Expected milestoneA return to the committee in early 2025, after further design work, public feedback, and commission review.18
Later recordThe fiscal 2026 first-quarter report anticipated a committee return in October – December 2025.26
FY2026 first-quarter report
Expected milestoneCommittee return in the second quarter, October – December 2025.26
Later recordThe second-quarter report anticipated a return in January – March 2026.26
The June 30, 2028 target concerns completion of design.26