Colorado Street Bridge · Project Guide
← Back to the project guide

Source tables and preserved records

These selected tables were transcribed and checked against the visible City document pages on September 13, 2026. They are reading aids, not replacement City records. Source wording and values are retained unless a note identifies a clarification.

2021 survey

Read both survey summaries and their limits →

Public Safety Committee · August 18, 2021 · Staff report · PDF p. 3

The survey ran from March 4 through May 31, 2021. The City received 2,268 responses overall, but 1,038 ranked the mockups.

Most preferred mockup, among 1,038 rankings
DesignVotesShare reported
Option A – Mesh (Curved-Straight)21620.8%
Option B – Mesh (Curved-Curved)46244.5%
Option C – Picket36034.7%
Total rankings1,038100.0%

The report separately records 622 comments, of which 44% preferred that barriers not be installed and that the bridge return to its original state without the temporary chain-link fence. Its Option C footnote says 59% listed that option as their least favorite. The footnote does not give a separate question count.

The percentage in the total row is calculated from the three percentages shown. People chose whether to take part, so their answers do not necessarily represent Pasadena residents as a whole. Design rankings and written comments were counted separately, using different totals. They should not be treated as the same result or compared directly with the later survey to show a change in opinion.

Police tables through June 13, 2021

Read the local-count summary and its coverage gaps →

Public Safety Committee · August 18, 2021 · Staff report · PDF p. 2

The source covers January 1, 2015 through June 13, 2021. The last row is a partial year. The incident categories below follow the source, with line breaks removed.

Police-reported incident categories
YearClimbed / attempted to climbDidn’t climbBreached fenceBetween fenceTotal
2015336N/A12
201621017N/A29
201751413N/A32
20184127124
20198143126
2020281415
2021 through June 1302125

“Didn’t climb” describes standing near the bridge and contemplating jumping. “Breached fence” describes going over the balustrade. “Between fence” describes being behind the temporary chain-link fence at an alcove. N/A is retained from the source, not converted to zero.

Separate Police Department suicide-death table
YearDeaths
20154
20162
201710
20184
20191
20200
2021 through June 131

Do not add the death counts to the incident table to infer a count of distinct events. These are separate source tables. The guide also identifies a contemporaneous report of nine deaths in 2017. This guide does not resolve that difference. These tables do not provide complete year-by-year counts for recent years.

2021 and 2022 fiscal sections

Read the project funding summary →

Public Safety Committee · August 18, 2021 · Fiscal section · PDF p. 5

The fiscal section reports $1.05 million appropriated and spent on installation and maintenance of temporary fencing, mockup design and installation, environmental assessment, conceptual design, and outreach. It estimates $4–6 million to complete design and construction. This paragraph is a summary, not a verbatim transcription.

Public Safety Committee · September 21, 2022 · Fiscal section · PDF p. 4

The 2022 section again describes the $1.05 million spent on those earlier activities and records an additional $2 million in ARPA funding in FY2022 for future phases. It says the actual cost cannot be determined until an option has been selected and its design completed. This is a summary.

These reports do not account for every budget approval, transfer, or payment through 2026. Adding their figures together will not show the money currently available. They do not establish whether the federal ARPA funding met its commitment requirements or other rules.

September 2022 schedule

Read how the project forecasts changed →

Public Safety Committee · September 21, 2022 · Staff report · PDF p. 3

Planned steps and dates in the September 2022 report
ActivityAnticipated timing
Public outreachNovember 2022–May 2023
Consultant awardDecember 2022 / January 2023
Design conceptsJanuary–June 2023
Historic Preservation CommissionJuly 2023
Design CommissionAugust 2023
Public Safety CommitteeSeptember 2023

Activity names are shortened for reading. These were planned dates, not confirmation that the work was completed. The February 9, 2023 newsletter later forecast a committee return by year-end. The presentation occurred on November 15, after the earlier September target.

How the approved project budget changed

Read the project funding summary →

The approved project budget reached $3,050,000: $950,000 from the General Fund, $100,000 in Gas Tax funding, and $2 million labeled ARPA, the federal American Rescue Plan Act. In 2025, the Council transferred $130,000 on June 9 and $46,000 on July 21 to the San Rafael Bridge Seismic Retrofit project, reducing the total to $2,874,000. Staff said enough remained to finish design without affecting its progress. Construction still required additional funding.

Project 73324 net appropriation
RecordChangeRunning total
FY2023 adopted budget, appropriated through FY2022$950,000 General Fund + $100,000 Gas Tax + $2,000,000 ARPA$3,050,000
June 9, 2025 approved transfer to San Rafael Bridge−$130,000 General Fund$2,920,000
July 21, 2025 approved transfer to San Rafael Bridge−$46,000 General Fund$2,874,000

The cited records establish the approved project budget. The amount remaining after outstanding commitments is unresolved, as is the project’s federal ARPA accounting.

Added September 15, 2026. Running totals are calculations from the cited records, not available cash balances.

FY2026 project 73324 row

Read the funding and schedule summary →

Finance & Audit Committee · August 24, 2026 · Packet PDF p. 184 excerpt · Full packet

The monitoring report is dated July 21, 2026 and covers activity through June 30, 2026. The row appears on packet PDF p. 184 and internal report p. 4.

Colorado Street Bridge Barrier Enhancements – Design Phase
Source fieldReported value
Priority6
Project number73324
Total estimated cost$2,874,000
Appropriation through FY2026$2,874,000
Expenditures, life of project$1,475,508
Percent of appropriations spent to date51%
FY2026 workplan scheduleDesign and environmental documentation will continue in FY2026.
Status updateFurther evaluation of concepts by Pasadena Heritage continued in the fourth quarter.
Target completion dateJune 30, 2028
Revised completion dateBlank in source
PhaseOngoing

Currency symbols and date formatting were added for clarity. This row covers the design phase. It is not a budget for all construction work or a promise of when the barrier will be built. “Life of project” does not mean spending in FY2026 alone.

Original documents, searchable copies, and how the copies were made

The original City documents remain the sources. The 2021 and 2022 reports are scanned images, so their words cannot be searched in the original files. The copies below add computer-recognized text so readers can search them. The original page images are unchanged.

Text recognition can misread words, numbers, or their order on the page. Adding searchable text does not guarantee that a PDF works well with assistive technology. The web tables above offer another way to read the selected figures. If a copy differs from the original, check the original page image.